Site visit report format
By the Inbecto team · Updated
A site visit report records one visit: the project, date, who visited and why, progress against plan, people on site, what is wrong and what must be done, by whom and by when. Write it the same day, attach photos, and send it to the client or the team so decisions are on record.
Free, no sign-up. Filled with the sample below: change it to your own details. In the Excel file the amounts and totals are formulas.
When you need it
- A weekly or stage check on a running site
- A visit before ceiling boarding, tiling or handover
- A client or architect visit where instructions are given
What to include
| Field | What goes in it |
|---|---|
| Project, date and visited by | And the purpose of the visit. |
| Progress | Percent done against what was planned. |
| People and work on site | Who was working, on what. |
| Observations | Area by area, what was seen. |
| Action, by whom, by when | One owner and one date for each. |
| Client instructions | Changes asked for, to be priced. |
| Photos and next visit | Numbered photos, and the next date. |
Sample site visit report format
SITE VISIT REPORT
From
Shree Windows & Interiors
Plot 18, Sector 37, Gurugram, Haryana 122001
GSTIN 06ABCPS1234K1Z8 · Phone 98110 00000
Project
Malhotra residence
Flat 1203, Tower B, Green Avenue, Sector 92, Gurugram
- Date:
- 14 Nov 2026
- Visited by:
- Anil Sharma, site engineer
- Purpose:
- Weekly check before false ceiling boarding
- Progress:
- 45% done (50% planned)
- On site:
- 6 people: 2 electricians, 3 ceiling fixers, 1 helper
| Sr | Area | Observation | Action | By | By when |
|---|---|---|---|---|---|
| 1 | Living room ceiling | Grid fixed; AC drain pipe not laid yet | Lay and test the drain before boarding | Plumber | 17 Nov |
| 2 | Kitchen | Sink outlet 4 in off the drawing | Shift to match kitchen drawing K-02 | Plumber | 17 Nov |
| 3 | Master bedroom | Wardrobe wall out of plumb by 10 mm | Pack the frame; tell the factory | Carpentry | 19 Nov |
| 4 | Balcony | Gap at the sill of window W5 | Seal with silicone after glazing | Window team | 21 Nov |
| 5 | Store | Bathroom 2 tiles short by 6 boxes | Order 6 boxes of the same batch | Purchase | 18 Nov |
Client instructions
Two more sockets beside the bed in bedroom 2: add to the change list with price.
Photos
12 photos, numbered by area.
Next visit
21 Nov 2026, before ceiling boarding.
Visited by
Client or site in-charge
Make this in Inbecto
Site visits and Site reports
Inbecto books visits on Site visits, with the purpose, the person going, photos from the phone and notes, and marks them done. Site reports are the daily reports from site: weather, progress %, manpower, work done, plan for tomorrow, issues, instructions given and visitors. Supervisors file them from their phone, and they show on the project's Site tab.
- Schedule the visit on Site visits with its purpose and person
- On site, add photos and notes, and mark the visit Done
- For daily reports, press New report on Site reports
- Fill in progress, manpower, work done, issues and instructions
- Follow the project's Site tab for progress and money due